Preamble :
1. The Central
Government vide Notification No. GSR 329 (E) dated 10.04.2003 and
No. GSR 330 (E) dated 10.04.2003 amended the Mineral Concession
Rules, 1960 and Mineral Conservation and Development Rules, 1988
respectively. As per these amendments all the existing mining
lessees are required to submit the "Progressive Mine Closure
Plan" along with prescribed financial sureties within 180
days from date of notification. Further, the mining lessee is
required to submit "Final Mines Closure Plan" one year
prior to the proposed closure of the mine. In the notification it
has been enumerated that the "Progressive Closure Plan"
and "Final Closure Plan" should be in the format and as
per the guidelines issued by the Indian Bureau of Mines.
2. Mine closure
encompasses rehabilitation process as an ongoing programme
designed to restore physical, chemical and biological quality
disturbed by the mining to a level acceptable to all concerned.
It must aim at leaving the area in such a way that rehabilitation
does not become a burden to the society after mining operation is
over. It must also aim to create as self-sustained ecosystem.
3. Mine closure
operation is a continuous series of activities starting from day
one of the initiation of mining project. Therefore, progressive
mine closure plan will be an additional chapter in the present
mining plan and will be reviewed every five years in the Scheme
of Mining. As progressive mine closure is a continuous series of
activities, it is obvious that the proposals of scientific mining
have had included most of the activities to be included in the
progressive mine closure plan. Therefore, reference to relevant
paragraphs and a gist of the same in progressive mine closure
plan will be sufficient.
4. Final mine
closure plan as per statute, shall be considered to have its
approval at least nine months before the date of proposed closure
of mine. This period of nine months is reckoned as preparatory
period for final mine closure operations. Therefore, all
proposals for activities which have to be carried out after
production of mineral from the mine or mining is ceased, shall be
included in the final mine closure plan. The final mine closure
plan will thus be a separate document with detailed chapters as
per guidelines given below.
The mine closure
plan will be prepared as per the guidelines given as enclosure.
The guidelines include the specific activities both in
progressive mine closure plan and final mine closure plan.
ENCLOSURE
GUIDELINES FOR
MINE CLOSURE PLAN
1.
Introduction:
The name of the
lessee, the location and extent of lease area, the type of lease
area (forest, non-forest etc), the present land use pattern, the
method of mining and mineral processing operations, should be
given.
1.1 Reasons
for closure : The reasons for closure of mining operations
in relation to exhaustion of mineral, lack of demand, uneconomic
operations, natural calamity, directives from statutory
organisation or court etc. should be specified.
1.2 Statutory
obligations : The legal obligations, if any which the lessee
is bound to implement like special conditions imposed while
execution of lease deed, approval of mining plan, directives
issued by the Indian Bureau of Mines, conditions imposed by the
Ministry of Environment and Forests, State of Central Pollution
Control Board or by any other organisation describing the nature
of conditions and compliance position thereof should be indicated
here (the copies of relevant documents may be attached as
Annexure).
1.3 Closure
plan preparation : The names and addresses of the applicant
and recognised qualified person who prepared the Mine Closure
Plan and the name of the existing agency should be furnished. A
copy of the resolution of the Board of Directors or any other
appropriate administrative authority as the case may be on the
decision of closure of mine should be submitted.
2. Mine Description:
2.1 Geology: Briefly
describe the topography and general geology indicating rock types
available, the chemical constituents of the rocks / minerals
including toxic elements if any, at the mine site.
2.2 Reserves : Indicate the mineral reserves available category wise in the
lease area estimated in the last mining plan / mining scheme
approved along with the balance mineral reserves at the proposed
mine closure including its quality available ( for final mine
closure plan only).
2.3 Mining Method : Describe in brief the mining method followed to win the mineral,
extent of mechanisation , mining machinery deployed, production
level etc.
2.4 Mineral Beneficiation : Describe in brief the mineral beneficiation practice if any
indicating the process description in short. Indicate discharge
details of any tailings / middlings and their disposal /
utilisation practice followed.
3. Review of
Implementation of Mining Plan / Scheme of Mining including five
years Progressive Closure Plan upto final closure of mine:
Indicate in detail the various
proposals committed with special emphasis on the proposals for
protection of environment in the approved Mining Plan / Scheme of
Mining including five years Progressive Closure Plan upto the
closure of mine vis-a-vis their status of implementation.
Highlight the areas, which might have been contaminated by mining
activities and type of contaminants that might be found there. The
reasons for deviation from the proposals if any with corrective
measures taken should also be given.
4.Closure Plan :
4.1 Mined-Out Land : Describe the proposals to be implemented for reclamation and
rehabilitation of mined-out land including the manner in which
the actual site of the pit will be restored for future use. The
proposals should be supported with relevant plans and sections
depicting the method of land restoration / reclamation /
rehabilitation.
4.2 Water Quality
Management : Describe in detail the existing surface and
ground water bodies available in the lease areas and the measures
to be taken for protection of the same including control of
erosion, sedimentation, siltation, water treatment, diversion of
water courses , if any, measures for protection of contamination
of ground water from leaching etc. Quantity and quality of
surface water bodies should also be indicated and corrective
measures proposed to meet the water quality conforming the
permissible limits should also be described. Report of
hydrological study carried out in the area may also be submitted.
The water balance chart should be given. If there is potential of
Acid Mine Drainage the treatment method should be given.
4.3 Air Quality Management
: Describe the existing air quality status. The corrective
measures to be taken for prevention of pollution of air should be
described.
4.4. Waste Management : Describe the type, quality and quantity of overburden, mineral
reject etc. available and their disposal practice. If no
utilisation of waste material is proposed, the manner in which
the waste material will be stabilised should be described. The
protective measures to be taken for prevention of siltation,
erosion and dust generation from these waste material should also
be described. If toxic and hazardous elements are present in the
waste material the protective measures to be taken for prevention
of their dispersal in the air environment, leaching in the surface
and ground water etc, should be described.
4.5 Top Soil Management : The top soil available at the site and its utilisation should be
described.
4.6 Tailing Dam Management
: The steps to be taken for protection and stability of
tailing dam, stabilisation of tailing material and its
utilisation, periodic desilting, measures to prevent water
pollution from tailings etc., arrangement for surplus water
overflow alongwith detail design, structural stability studies,
the embankment seepage loss into the receiving environment and
ground water contaminant if any should be given.
4.7 Infrastructure : The existing infrastructural facilities available such as roads,
aerial ropeways, conveyer belts, railways, power lines, buildings
& structures, water treatment plant, transport, water supply
sources in the area etc. and their future utilisation should be
evaluated on case to case basis. If retained, the measures to be
taken for their physical stability and maintenance should be
described. If decommissioning proposed, dismantling and disposal
of building structures, support facilities and other
infrastructure like electric transmission line, water line, gas
pipeline, water works, sewer line, telephone cables, underground
tanks, transportation infrastructure like roads, rails, bridges,
culverts etc., electrical equipments and infrastructures like
electric cables, transformers to be described in connection with
restoring land for further use.
4.8 Disposal of Mining
Machinery : The decommissioning of mining machineries and
their possible post mining utilisation, if any, to be described.
4.9 Safety and Security : Explain
the safety measures implemented to prevent access to surface
openings, excavations etc., and arrangements proposed during the
mine abandonment plan and upto the site being opened for general
public should be described.
4.10 Disaster Management
and Risk Assessment : This should deal with action plan for
high risk accidents like landslides, subsidence flood, inundation
in underground mines, fire, seismic activities, tailing dam
failure etc. and emergency plan proposed for quick evacuation,
ameliorative measures to be taken etc. The capability of lessee
to meet such eventualities and the assistance to be required from
the local authority should also be described.
4.11 Care and maintenance
during temporary discontinuance : For every five yearly
review ( as given in the mining scheme), an emergency plan for
the situation of temporary discontinuance or incomplete programme
due to court order or due to statutory requirements or any other
unforeseen circumstances, should include a plan indicating
measures of care, maintenance and monitoring of status of
unplanned discontinued mining operations expected to re-open in
near future. This should detail item wise status monitoring and
maintenance with periodicity and objective.
5. Economic
Repercussions of closure of mine and manpower retrenchments :
Manpower retrenchment,
compensation to be given, socio-economic repercussions and
remedial measures consequent to the closure of mines should be
described, specifically stating the following.
5.1 Number of local residents
employed in the mine, status of the continuation of family
occupation and scope of joining the occupation back.
5.2 Compensation given or to be
given to the employees connecting with sustenance of himself and
their family members.
5.3 Satellite occupations
connected to the mining industry - number of persons engaged
therein - continuance of such business after mine closes.
5.4 Continued engagement of
employees in the rehabilitated status of mining lease area and
any other remnant activities.
5.5 Envisaged repercussions on
the expectation of the society around due to closure of mine.
6. Time Scheduling for
abandonment : The details of time schedule of all
abandonment operations as proposed in para 4 should be described
here. The manpower and other resources required for completion of
proposed job should be described. The schedule of such operations
should also be supplementated by PERT ( Programme Evaluation
& Review Technique ), Bar chart etc.
7. Abandonment Cost : Cost
to be estimated based on the activities required for implementing
the protective and rehabilitation measures including their
maintenance and monitoring programme.
8. Financial Assurance : The
financial assurance can be submitted in different forms as stated
in Rule 23(F)(2) of Mineral Conservation and Development
(amendment) Rules, 2003. In the mine closure plan, the manner in
which financial assurance has been submitted and its particulars
have to be indicated. For Model Bank Guarantee
Form , please click here.
9. Certificate : The
above mentioned actions have been taken to be stated clearly in
the mine closure plan. A certificate duly signed by the lessee to
the effect that said closure plan complies all statutory rules,
regulations, orders made by the Central or State Government,
statutory organisations, court etc. have been taken into
consideration and wherever any specific permission is required
the lessee will approach the concerned authorities. The lessee
should also give an undertaking to the effect that all the
measures proposed in this closure plan will be implemented in a
time bound manner as proposed.
10. Plans, Sections etc.
: The chapter
1,2,3 and 4 should be supported with Plans and Sections. The
Closure Plan may also be submitted depicting photographs,
satellite images on compact disc etc. wherever possible.
NOTE
1. The mine closure plan in
progressive stage will be prepared by paragraphs where
sub-paragraphs may be added for detailed items whereas the final
mine closure plan will be prepared in chapters with sub-chapters
as necessary with adequate details.
2. The guidelines for the both
the documents will be same as above.